| 流江河1#桥深水桩基础填充式双壁钢围堰设计(49 卷) |
| 英文标题 |
| Design on steel cofferdam in form of two walls with filled concrete between them used in casting of deep-water pile foundation for Liujianghe river bridge No 1 |
| 摘要 |
| 达成铁路扩能改造工程流江河大桥深水桩施工为本管段内的重点控制性工程,在工程质量、进度、安全等各方面均提出了较高的要求。在施工过程中先加工双层薄壁钢围堰,然后在内外壁间充填C20混凝土以提高围堰整体承载能力,取得良好效果,在保证工程质量的前提下取得较好的经济效 |